Crenshaw/LAX Transit Project begins construction

PastedGraphic-1.jpg

Posted on Metro's blog The Source on Posted February 5, 2014 by Jose Ubaldo:

The Crenshaw/LAX Transit Project this week began construction activities along the 8.5-mile alignment that includes old railroad track demolition, building demolition and tree removal and pruning.

The contractor Walsh/Shea Corridor Constructor (WSCC) began removing old railroad tracks at two locations: Florence Avenue between Crenshaw Boulevard and Manchester Avenue and Aviation Boulevard between Manchester Avenue and Imperial Highway.

The work will be done between 7 a.m. and 3:30 p.m. Monday through Friday and will last for the next four months. No traffic impacts are expected since this will be done in Metro’s right-of-way.

The demolition of buildings at the northeast corner of Crenshaw Boulevard and Rodeo Road will have the same work schedule but is expected to be completed in two weeks. At the same location trees will be removed beginning Thursday, Feb. 6. This is expected to take only two days and will have the same work schedule. This location will be used as a construction yard and will ultimately be the location of a future underground station.

In addition, tree pruning will take place at four locations along Crenshaw Boulevard: between Exposition Boulevard and Rodeo Road, between Martin Luther King Jr. Boulevard and Stocker Street both sides of Crenshaw Boulevard and both sides between 43rd Place and 43rd Street.

The last location will be the center island at Crenshaw and 48th Street.